Burlingame Community for Education Lunch - Child Nutrition Parent Organizations Safe Routes to School School Directory and SARCs School Emergency Guidelines Wellness Services
About BSD Superintendent Board of Trustees Business Services Educational Services Facilities Special Education Department Technology Inspect Winter 2018 Assessments
Current Openings, Salary Schedules and Union Agreements Becoming a Teacher in San Mateo County Employee Benefits Employee Safety Plan with IIPP
Returning Student Registration 2017 2018 New Student Registration District Boundaries 2018 2019 New Student Registration

Facility News

Roosevelt and Washington Elementary School Classroom Wing Project RFP - Questions and Answers

Questions Answer
Can you tell me the engineers estimate for the projects?

Exhibit A-1

Roosevelt Elementary School Classroom Wing Project

Project Estimate:  $4,780.000

Washington Elementary School Classroom Wing

Project Estimate:  $4,570.000

The RFQ response requires “a current DSA PC number which would be applicable for the specific building configuration anticipated as a part of the Project.”  Of course this would be the only way to meet the completion deadline of August 17, 2018.  We don’t have a PC for this plan nor do we know anyone that does.  The building spec’s. look pretty typical for us. 


Do you know a building vendor with this PC?

See Addendum 1

When will Addendum 1 be issued?

Issued today as two documents.

Both can be referred to in whole as "Addendum 1" on the Bid Form

Is there flexibility on completion date still of August 2018 for both sites? While the proposals for this project will be based on an August 2018 completion.  Actual contract completion date will be negotiated as part of the Lease based upon actual production of modular buildings and covered walkways
What is the timing for DSA approval of the sitework component? Is the sitework package ready to be submitted/approved at the over-the-counter appointment for the buildings/canopy PC’s or will it be submitted and approved separately? The purpose of this question is to determine if the sitework can commence sooner in the schedule?

We will be submitting the site work package for DSA approval in January, and expect it to be approved by March, possibly sooner.  Because we don't expect the site package to be literally over the counter, we expect the submittal will be separate and earlier than the building/canopy submittal.  Our intent is to allow the contractor to begin sitework early on Roosevelt.